Construction timelines for Member housing at Falcon Way

Please be advised that construction is scheduled to commence on Dec. 16 at the 36-unit Member housing development at Falcon Way (2261 Tsawwassen Drive).

Dec. 16-20: Clearing most of existing trees on the property.

Jan. 6- Feb. 20: Site stripping and raising the site (preload).

As part of the tree-clearing operation, wood will be cut into 12-16″ rounds and placed nearby for TFN Members to pickup for their personal use. The wood will be available for pickup from Dec. 20- Jan. 30.

Should you have any questions, please contact TFN Lands at 604.948.0694.