Please be advised that Quantum Murray Environmental will be setting up another exclusion zone the evening of April 01 to complete the remaining hazardous container remediation work. This is a precautionary measure, and the work is expected to be completed quickly.

Closure Details:

  • Date: April 1, 2025 (16:30) – April 2, 2025 (06:00)

  • Location: Same area as the previous exclusion zone

Schedule:

  • April 1

    • 16:30 – Closure of the berth area begins

    • 20:00 – 300-meter exclusion zone reinstated for eight hours

  • April 2

    • 04:00 – Exclusion zone reduced to 50 meters

    • 06:00 – Normal operations resume

For safety reasons, the designated areas will be closed to all personnel. Thank you for your patience. If there are any schedule changes, updates will be provided. Please reach out with any questions.